Do I need an arc flash study in the UK?
Short answer: no UK regulation names an arc flash study, but UK law requires you to prevent electrical danger and to assess risk — and where people work on or near energised equipment, an arc flash study is the recognised way to show that the risk has been assessed properly.
What the law requires
Regulation 4 of the Electricity at Work Regulations 1989 requires electrical systems to be constructed, maintained and worked on so as to prevent danger, so far as is reasonably practicable. The Management of Health and Safety at Work Regulations 1999 require a suitable and sufficient risk assessment. UK law is goal-setting: it tells duty holders what to achieve, not which calculation to run.
The IET publishes an Arc flash risk management Factfile that sets out a risk-based approach and points duty holders towards competent assessment.
When an arc flash study is worth doing
- People switch, test, rack breakers or work near exposed conductors on energised LV or MV equipment
- The site has large transformers, generators or high fault levels, such as data centres, industrial plants, utilities and solar or battery sites
- The network has changed: a new transformer, generator, supply upgrade or protection setting change
- You need to choose arc-rated PPE and need evidence for the level you specify
- An insurer, client or auditor asks for the evidence behind your electrical risk assessment
Working dead remains the default in the UK. The study helps you decide where live work can be justified, which controls are needed, and where design or protection changes would remove the hazard.
What a study involves
- Collecting single-line diagrams, cable, transformer, generator and protection data — on site where records are incomplete
- Building an ETAP model and calculating fault levels to IEC 60909
- Calculating incident energy and arc flash boundaries at each board to IEEE 1584
- Producing arc flash labels and a report with recommendations to reduce the energy, such as faster protection settings
How much does it cost?
Cost depends on the size of the network and the quality of existing records. As one published example, a UK contractor quotes about £7,750 for a typical system with four transformers (Freedom / NG Bailey). Good drawings and settings records reduce the cost.
Next step
eGearZone carries out ETAP arc flash studies for UK sites, with protection co-ordination studies where settings need to change. Request a study quote.